A person-hour is the amount of work that the average worker can do in one hour. It is anticipated that a company-wide system upgrade will take approximately 60 person-hours to complete. How long will it take five technicians to perform the refresh?

IT Exam Items Repository › A person-hour is the amount of work that the average worker can do in one hour. It is anticipated that a company-wide system upgrade will take approximately 60 person-hours to complete. How long will it take five technicians to perform the refresh?

A person-hour is the amount of work that the average worker can do in one hour. It is anticipated that a company-wide system upgrade will take approximately 60 person-hours to complete. How long will it take five technicians to perform the refresh?

  • 5 hours
  • 8 hours
  • 10 hours
  • 12 hours