A team of engineers has identified a solution to a significant network problem. The proposed solution is likely to affect critical network infrastructure components. What should the team follow while implementing the solution to avoid interfering with other processes and infrastructure?
- syslog messages and reports
- one of the layered troubleshooting approaches
- knowledge base guidelines
- change-control procedures
Explanation: Change-control procedures should be established and applied for each stage to ensure a consistent approach to implementing the solutions, and to enable changes to be rolled back if they cause other unforeseen problems.