A company informs the account manager that the installation of a new edge router at the customer remote branch location cannot be done at the scheduled time because of a large order that the branch office needs to complete. As a result, the end date of the project must be adjusted to accommodate the additional time. What is the action should the account manager take?
- Cancel the order for the new edge router.
- Work with designer to redesign the branch network.
- Instruct the technician to complete the install of the router at on the date in the contract.
- Adjust the timeline documentation to show the company how the delay will affect the project completion date.
Exam with this question: CCNA Discovery 4: DCompNtwk Chapter 9 Exam