A company informs the account manager that the installation of a new edge router at the customer remote branch location cannot be done at the scheduled time because of a large order that the branch office needs to complete. As a result, the end date of the project must be adjusted to accommodate the additional time. What is the action should the account manager take?

IT Questions BankCategory: CCNA Discovery v4A company informs the account manager that the installation of a new edge router at the customer remote branch location cannot be done at the scheduled time because of a large order that the branch office needs to complete. As a result, the end date of the project must be adjusted to accommodate the additional time. What is the action should the account manager take?

A company informs the account manager that the installation of a new edge router at the customer remote branch location cannot be done at the scheduled time because of a large order that the branch office needs to complete. As a result, the end date of the project must be adjusted to accommodate the additional time. What is the action should the account manager take?

  • Cancel the order for the new edge router.
  • Work with designer to redesign the branch network.
  • Instruct the technician to complete the install of the router at on the date in the contract.
  • Adjust the timeline documentation to show the company how the delay will affect the project completion date.

Exam with this question: CCNA Discovery 4: DCompNtwk Chapter 9 Exam