Question:
A person-hour is the amount of work that the average worker can do in one hour. It is anticipated that a company-wide system upgrade will take approximately 60 person-hours to complete. How long will it take five technicians to perform the refresh?
- 5 hours
- 8 hours
- 10 hours
- 12 hours