In addressing an identified risk, which strategy aims to stop performing the activities that create risk?

IT Questions BankCategory: CCNA CyberOpsIn addressing an identified risk, which strategy aims to stop performing the activities that create risk?

In addressing an identified risk, which strategy aims to stop performing the activities that create risk?

  • risk retention
  • risk avoidance
  • risk sharing
  • risk reduction

Explanation:

There are four potential strategies for responding to risks that have been identified:

  • Risk avoidance – Stop performing the activities that create risk.
  • Risk reduction – Decrease the risk by taking measures to reduce vulnerability.
  • Risk sharing – Shift some of the risk to other parties.
  • Risk retention – Accept the risk and its consequences.

Exam with this question: CCNA Cyber Ops Chapter 10 Exam Answers
Exam with this question: Modules 21 - 23: Cryptography and Endpoint Protection Group Exam

Subscribe
Notify of
guest

0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x