There are four potential strategies for responding to risks that have been identified:

  • Risk avoidance – Stop performing the activities that create risk.
  • Risk reduction – Decrease the risk by taking measures to reduce vulnerability.
  • Risk sharing – Shift some of the risk to other parties.
  • Risk retention – Accept the risk and its consequences.