Refer to the exhibit. An administrator documented the output of a CAM table from an Ethernet switch as shown. What action will the switch take when it receives the frame shown at the bottom of the exhibit?

IT Questions BankCategory: CCNA 3 v4Refer to the exhibit. An administrator documented the output of a CAM table from an Ethernet switch as shown. What action will the switch take when it receives the frame shown at the bottom of the exhibit?

Refer to the exhibit. An administrator documented the output of a CAM table from an Ethernet switch as shown. What action will the switch take when it receives the frame shown at the bottom of the exhibit?

  • discard the frame
  • forward the frame out port 2
  • forward the frame out port 3
  • forward the frame out all ports
  • forward the frame out all ports except port 3
  • add station 00-00-3D-1F-11-05 to port 2 in the forwarding table

Exam with this question: CCNA Exploration 3: ESwitching Final Exam

Subscribe
Notify of
guest

0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x