Refer to the exhibit. Which statement is true about PPP operation?
- Layer 2 is down.
- LCP, IPCP, and CDPCP negotiations are in progress.
- Only the link-establishment phase completed successfully.
- Both the link-establishment and network-layer phase completed successfully.
Exam with this question: CCNA Exploration 4: EWAN Chapter 2 Exam