Which risk management plan involves discontinuing an activity that creates a risk?
- risk reduction
- risk retention
- risk avoidance
- risk sharing
Explanation: During a risk assessment it may be determined that an activity involves more risk than benefit. In such a situation an organization may decide to avoid the risk altogether by discontinuing the activity. This is known as risk avoidance.